PT PII is backing the Jatiluhur I regional water supply project through access to a government guarantee, so that banks lend to infrastructure development with more confidence, according to ANTARA.
Acting president director of PT PII Donny Hamdani said the guarantee brings public service needs together with investment by business entities. Of the Rp1.75 trillion in guaranteed investment, about 70 percent, or Rp1.2 trillion, comes from bank loans.
Capital composition and plant capacity
About 30 percent, or Rp554 billion, of the total investment is met through equity participation by the business entity, ANTARA reported. The implementing company, PT Wika Tirta Jaya Jatiluhur, views the government guarantee as crucial to the banks' decision because it lowers the project's risk profile.
Donny Hamdani said the guarantee could also improve financing quality through longer tenors and lower interest rates. The installation has a treatment capacity of 4,750 liters per second and is described as one of the largest regional plants in Indonesia.
Its water is intended for DKI Jakarta, Kota Bekasi, Kabupaten Bekasi and Kabupaten Karawang through their respective regional water companies. PT Wika Tirta Jaya Jatiluhur president director Rendy Ardiansyah said the Rp1.75 trillion project financing came from a combination of loans and company capital, CNBC Indonesia reported.
Financing journey and cooperation period
WTJJ held its first financial close in 2023 with conventional loans and refinanced at the end of 2025. The central government builds the main infrastructure, while regional governments handle distribution networks down to household connections.
PII also provides guarantee coverage supporting Perum Jasa Tirta II's payments to WTJJ of up to Rp125 billion if those obligations are unmet, according to CNBC Indonesia. The public-private partnership runs 34 years and 11 months, from the start of construction on 19 January 2022 until 19 December 2056.
Who is affected
Commercial operation began on 18 December 2024, and first-year uptake reached 1,096 liters per second, above the initial plan of 386 liters per second, CNBC Indonesia reported.
Uptake of 1,096 liters per second in the first commercial year compares with the 386 liters per second planned before operations began.
What is still unclear
The bulk water tariff agreed among the parties in the Jatiluhur I project has not been disclosed. It is also unclear which alternative financing model the Ministry of Public Works (Kementerian PU) is reviewing for other regional water supply projects.
How costs will be shared between the central government and regional governments after the cooperation period ends has not been settled publicly. No timeline was disclosed for that decision, and no figures were released for the split.